Is it permissible for an engineer to agree with a subcontractor to supply a fence at a price of 200 riyals per meter, while taking a percentage of the profit, knowing that the lowest price offered to the company is 300 riyals per meter, and the actual supply price is 100 riyals per meter?

Share this answer

Source: FtawySummary from Ftawy's records · added here Sep 2, 20261 min readAlso available in العربية
The answer

If the work is carried out under assignment and authorization from the company, then it is not permissible to take a commission from the institution unless the company gives permission. However, if the work is done independently outside official working hours, then there is no harm in taking a commission from the institution for the referral.

Summary from Ftawy's records · added here

Reviewed by El Fatwa's sharia committee.

Read the full answer on Ftawy
Where this answer came from
Source platform
Ftawy
Original fatwa ID
152930
Added here
. This is when the answer was added to El Fatwa, not the fatwa's date.
Text
Summary from Ftawy's records, reviewed by El Fatwa's sharia committee.
Read the full ruling
Read the full answer on Ftawy