Is the engineer entitled to demand payment from the client for the excess square footage of ceramic tiles that the client was unable to return to the store due to the engineer's delay in installation?
Source: FtawySummary from Ftawy's records · added here Sep 2, 2026
This issue is closer to arbitration and requires details and hearing from both parties. If the questioner is an agent for the engineer in purchasing ceramics, then the purchase belongs to the principal, not the agent, and ownership and contractual rights pertain to the principal. If the principal instructs his agent to purchase a specific quantity, then whatever remains of this quantity with the principal is his property and responsibility, and he cannot compel the agent to take it and pay its price.
Summary from Ftawy's records · added here
Reviewed by El Fatwa's sharia committee.
Read the full answer on Ftawyhttps://ftawy.com/en/questions/188999
Where this answer came from
- Source platform
- Ftawy
- Original fatwa ID
- 188999
- Added here
- . This is when the answer was added to El Fatwa, not the fatwa's date.
- Text
- Summary from Ftawy's records, reviewed by El Fatwa's sharia committee.
- Read the full ruling
- Read the full answer on Ftawy