What is the ruling of the Sharia on an engineer who agrees with a client on a price for a project, then delegates its completion to another engineer for a lower price, with the difference being profit for the first engineer, without the knowledge of the client or the second engineer?

Share this answer

Source: FtawySummary from Ftawy's records · added here Sep 2, 20261 min readAlso available in العربية
The answer

There is no objection to the hired person subcontracting another to perform a task in a lease contract () for a work that is due (fi al-dhimmah), whether for the same wage, less, or more, as long as the work does not vary depending on who performs it. This is unless the first hirer stipulated that the hired person must perform the work himself.

Summary from Ftawy's records · added here

Reviewed by El Fatwa's sharia committee.

Read the full answer on Ftawy
Where this answer came from
Source platform
Ftawy
Original fatwa ID
184977
Added here
. This is when the answer was added to El Fatwa, not the fatwa's date.
Text
Summary from Ftawy's records, reviewed by El Fatwa's sharia committee.
Read the full ruling
Read the full answer on Ftawy