Is it permissible for a subcontractor to pay another subcontractor part of the value of work the latter has completed to expedite receiving his money, in exchange for the first subcontractor receiving the full value from the main company after a month and benefiting from the difference?

Share this answer

Source: FtawySummary from Ftawy's records · added here Sep 2, 20261 min readAlso available in العربية
The answer

The transaction mentioned, which is the contractor selling his debt to the company for accelerated cash payment, is a form of forbidden debt sale, because it leads to usury (riba). It is not permissible to sell a deferred debt to anyone other than the debtor for an accelerated or deferred cash payment, whether it be of the same type or a different type, because that involves selling a debt for a debt (بيع الكالئ بالكالئ), which is prohibited.

Summary from Ftawy's records · added here

Reviewed by El Fatwa's sharia committee.

Read the full answer on Ftawy
Where this answer came from
Source platform
Ftawy
Original fatwa ID
166409
Added here
. This is when the answer was added to El Fatwa, not the fatwa's date.
Text
Summary from Ftawy's records, reviewed by El Fatwa's sharia committee.
Read the full ruling
Read the full answer on Ftawy